The foundation footings were in place for Southern Academy’s new classroom and shelter building, and the block walls were up one course above the slab, as of Tuesday, Oct. 20, builder Frank Kelly of WAR Construction said.
Once the block cells and the slab are poured, crews will begin building the walls, Kelly said.
“So far, the project has gone very smoothly,” he said. “The subcontractors have been terrific to work with, and their work has consistently been completed on schedule or ahead of schedule.”